Sea Tank Project


After patiently waiting for our sea tanks to be replaced, we are finally beginning this project! The project went out to bid in January and Brang Construction was selected. The Greater Boca Raton Beach and Park District originally set aside $1 million for this project. Because such favorable bids were received, the District unanimously voted to approve an additional $1 million to complete the entire project rather than phasing it over a few years. Click here for more information about the project. Continue reading below for weekly updates on the progress!

Visit our YouTube site for videos of the project! Click here. 

 


February 10, 2012


 


February 5, 2012


January 27, 2012


 


 

January 18, 2012


 


January 12, 2012



January 6, 2012

 


December 29, 2011



 


December 22, 2011

 


December 15, 2011


December 8, 2011


 

December 1, 2011

 

 


November 21, 2011

 


November 17, 2011


 November 9, 2011

 


November 4, 2011



 


October 28, 2011

 


October 19, 2011

 

 


October 12, 2011

 


 

October 6, 2011


 

September 29, 2011


September 22, 2011

 


September 15, 2011

 

 


 

September 10, 2011


August 31, 2011

 


August 26, 2011


August 17, 2011


August 12, 2011

 


 

August 4, 2011


July 28, 2011


July 20,2011



July 15, 2011

The crew is working hard in this heat!


July 7, 2011


 


June 30, 2011

Lots of digging going on! Could we be seeing the footprints of the new tanks???

 

 


June 24, 2011

Test pilings were a success! The heavy equipment is busy drilling, installing and pouring. Pilings are in progress!




 


June 17, 2011

While it does not look like much is going, there is really important stuff happening! The construction crew has been working with the tests pilings that were installed about 2 weeks ago. After the cement is poured, it takes 7 days to set. Then the pilings undergo a pressure test. Successful tests mean the remaining pilings can be installed!


June 7, 2011

The big equipment is still here, doing what they need to do!


June 2, 2011

The heavy equipment has been moving in! A HUGE crane has arrived, and it is at work!

 

 


May 26, 2011

The demolition is just about complete. The tanks are gone. The walkways that were surrounding the tanks are gone. Trees have been moved. Ground has been smoothed.

Many of the trees that were in the tanks area have been moved to other areas of the property. Next time you drive in, you'll notice gumbo limbo trees in the grassy area on the south side of the driveway. On the north side, you'll see six cabbage palms. Talk a walk around the North trail and down by the Chiki, and you might see some other relocated trees!

About Us